Swap Sector Check
Purpose : to verify intalation mistake on feeder cable to BTS
1. Lock BCCH ARFCN each sector : Click Toolbar Lock on Channel (ie. BCCH Sect 1 = 547, Sect 2 = 540, Sect 3 = 543 )
2. Set HO Target : Equipment Properties -> Dedicated Mode -> Function -> Target HO (ie. BCCH 547, 540, 543)
3. Create drive route that can represent each sector
4. Export logfile into *.tab with IEs CI
5. Create thematic map for each CI (Cell Identity)
Picture above indicate swap sector between sector 2 and 3.
Hwalo om…
kayaknya sebelum di tematic harus di edit dulu datanya di mapinfo
di [b] table > Mintenance > table structure.[/b]
tentukan export logfile yang diinginkan, trus ganti type data CI dari integer ke character(5) jadi ntar hasilnya 16624 bukan 16,624 dari situ khan bisa di buat spider om 😛
BR,
| Posted 14 years, 10 months agoSinggih G
edit table structure dah ada di point 31 om,…
| Posted 14 years, 9 months agothanks
this good suggestion do u have sample reports (without confidential data) i would like to see the format and flow of the report.
| Posted 14 years, 7 months agosorry athula, i don’t have the sample report,…
if i have i’ll pm you,
thanks & regards
| Posted 14 years, 7 months agoisa
The example is fully swap feeder, what happen if it a partial swap? Its mean a dx1 at a dir but a dx2 at b dir?
hehehe
| Posted 14 years, 4 months agoHai Isa,
Thanks you very much to share basic info which very useful for me, looking forward another topic especially about Optimization KPI and DT that you all ready face previously.
Bravo!
| Posted 11 years, 9 months agoThanks for visiting pak Rino….
Need your advice to improve my knowledge pak….
Thank you,
| Posted 11 years, 9 months agoIsa
THANK YOU SO MUCH FOR ALL THE INFORMATION YOU HAVE SHARED.
| Posted 9 years, 9 months agowhat remains is practice and would want to join you.