Swap Sector Check
Purpose : to verify intalation mistake on feeder cable to BTS
1. Lock BCCH ARFCN each sector : Click Toolbar Lock on ChannelĀ
(ie. BCCH Sect 1 = 547, Sect 2 = 540, Sect 3 = 543 )

2. Set HO Target : Equipment Properties -> Dedicated Mode -> Function -> Target HO (ie. BCCH 547, 540, 543)

3. Create drive route that can represent each sector
4. Export logfile into *.tab with IEs CI
5. Create thematic map for each CI (Cell Identity)

Picture above indicate swap sector between sector 2 and 3.
Advertisement
Hwalo om…
kayaknya sebelum di tematic harus di edit dulu datanya di mapinfo
di [b] table > Mintenance > table structure.[/b]
tentukan export logfile yang diinginkan, trus ganti type data CI dari integer ke character(5) jadi ntar hasilnya 16624 bukan 16,624 dari situ khan bisa di buat spider om
BR,
| Posted 2 years, 7 months agoSinggih G
edit table structure dah ada di point 31 om,…
| Posted 2 years, 7 months agothanks
this good suggestion do u have sample reports (without confidential data) i would like to see the format and flow of the report.
| Posted 2 years, 5 months agosorry athula, i don’t have the sample report,…
if i have i’ll pm you,
thanks & regards
| Posted 2 years, 4 months agoisa
The example is fully swap feeder, what happen if it a partial swap? Its mean a dx1 at a dir but a dx2 at b dir?
hehehe
| Posted 2 years, 1 month ago